Tuesday 18 November 2014

Process Diagrams



We are utilizing / experimenting with a hybrid method of in-situ and panelization of the STIK system in order to construct the pavilion. The diagrams below illustrate the process we are currently working through in putting together the construct. 




Placement of markers on the site.


Placement of plywood base panels 


Installation of foundation modules


Installation of the entrance and side-boards


Placement of concrete anchoring blocks


In-Situ pouring of Row A utilizing our scanning system


Placement of prefabricated Row B panels


Bracing of Row B panels


Complete placement of Row B panels


Infill around Row B panels


Placement of prefabricated Row C panels


Complete placement of Row C panels


Placement of prefabricated Row D panels


Completion of Pavilion